Tabakfabrik Linz “Quadrill”

It starts in Linz

Zechner & Zechner ZT GmbH, together with the project developer and investor Bodner Bau GesmbH & Co KG, has won the competition for the so-called “Quadrill” on the site of the tobacco factory in Linz. An approximately 100 m high tower and base buildings are being built on the approximately 11,000 m² construction site. The planned garage encompasses the entire construction area and extends up to 15 m into the ground.

Made in Graz
Thomas Lorenz ZT GmbH is responsible for the statics. Securing the excavation, sealing and foundation proved to be tricky.

Services:
Project Information:
Leistungszeitraum.png
Period

2018-2023

Auftraggeber.png
Client

Bodner construction

Kosten.png
Construction costs

130.0 million

Geschossflaeche.png
Gross floor area

86.000 m²