Clean future
In the course of constructing a SNOx-plant (i.e. a combined flue gas de-sulphurisation and flue gas de-nitrification system) at the OMV Refining & Marketing GmbH in Wien Schwechat, SFL technologies GesmbH ordered static calculations to be carried out for the steel construction of the reactor, and the WSA-case and uptake flues.
Between autumn 2006 and summer 2007, 1,600 t of steel was used in the construction.
Project Information:
field of activity
Static-constructive processing
Detailed steel construction design for the plant reactor, WSA-case and uptake flues
Period
2006 - 2007
Client
SFL technologies GesmbH
Steel tonnage